Our client had a vision for their front entrance. Originally constructed in the 1930’s the concrete porch and walk had settled, cracked and weathered. The existing iron railing was failing and the landscaping was unimpressive, with overgrown and mismatched plantings.

The American Landscape team was charged with creating a front entry that complemented the home’s distinctive architecture and was visually stunning. The client wanted to maintain the original semi-circular layout of the porch landing and add a path to their south patio. The final design included a raised porch landing, primary and secondary walkways, a step at the junction to the city sidewalk, surrounding landscaping and lighting.  

Selecting the Right Materials for Texture, Color & Style 

Choosing the right materials is a critical aspect of creating the right aesthetic for a hardscape project. In this case, our team constructed the new front porch landing using Summit Stone® risers and full nose paver step treads. We flanked the lower step section with low-rise pillars of Summit Stone and Ledgestone caps. 

To introduce additional texture and pattern, the team built the porch landing and walkways with Elements pavers in a three-piece field pattern. A Brussel’s paver accent band is incorporated along the perimeter border, to accentuate the gentle curvilinear layout.

We eliminated an existing path of disheveled stepping stones that connected the front walk with a south side patio and replaced it with a paver walkway of the same materials as the primary front entry walk.

Our designer gave the colors of the materials careful consideration. The façade of the home is a cream brick veneer, so hardscape colors of cream, deep brown, tan and buff were carefully selected to complement and accentuate the home’s exterior.

Finishing Touches: Landscaping & Lighting

Our crew removed declining and overgrown landscaping from the front. We created a combination of formal and casual layouts using classic boxwoods, hydrangea, lilac and assorted perennials.

Low-voltage lighting from Kichler and Volt was used to enhance the night time atmosphere. Path light were positioned along the walkways, and under-cap accent lights were set on the entry pillars to create a soft welcoming glow as one approaches the front door.

Re-imagining the front entrance of this Wauwatosa, Wisconsin home was a challenge and rewarding for both our team and our very happy client.  

Ready to tackle your own dream project? Get in touch with our team today to start the conversation. (262) 252-4260

Before & After: Patio/Fire Pit Installation Despite Cold Temps!

Given the challenging winter conditions we have in Wisconsin, knowing how to complete hardscape installations even as colder temperatures begin is key. We’re sharing a behind-the-scenes look at the installation of a patio, walkway and fire pit for a client that we worked on well into January! The key for this installation was to lay frost blankets down on the work area well before frost and snow hardened the ground. Our team was able to complete almost all the installation and this client will now be top of the schedule for finishing off their project in spring.

You can watch our video of the project as it took shape, or read about the daily progress below.

Patio Installation: Day-by-Day Progress

Day 1
Orange frost blankets were placed weeks before the project was due to begin. Blankets had to be shoveled off, then lifted off the turf.  The area for the patio was then measured out and lines marked for crews to begin.

 

Day 2
Patio base excavation is completed and installation of the gravel patio base begins, along with the construction of the seat wall using Rosetta products.

Day 3
Building of the wall continues and on the other end of the patio, laying the gravel base is finished up.

Day 4
You can see the project really taking shape! The wall has been completed and Belgard pavers are being installed.

Day 5
The team continues laying pavers. Notice that any areas that are not being worked on are kept covered to protect the ground from freezing.

Day 6
The fire pit, using Rosetta products to match the seat wall is built. Work continues on leveling base and laying pavers.  In preparation for the installation of a pavilion in spring, the team inserts Sonotubes that will be filled with cement to create footings.

Day 7
Time to fill the Sonotubes with concrete! The last of the patio pavers are installed.  The team is careful to keep areas not being worked on covered so the project can keep progressing in the cold temps!

Day 8
Final day of this cold weather patio/firepit/walkway installation! The team used EdgeCrete to keep pavers in place and completed the walkway connecting the patio to the garage. The entire area was then cleaned and covered until work can resume in spring.

Extending the season for hardscape installations is one of the ways we deliver on our commitments to our customers. If you are ready to talk about your own landscaping project, get in touch with one of our talented designers today! (262) 252-4260

 

Want to stay in the loop?
Sign up for our newsletter.

"*" indicates required fields

Name*
This field is for validation purposes and should be left unchanged.

American Landscape - 50 Years of Outstanding Landscaping Service to the Greater Milwaukee Area

(262)252-4260
info@amerlandscape.com

N60 W16073 Kohler Ln,
Menomonee Falls, WI 53051